Water Infrastructure Group P/L
Smythesdale, Victoria 3351
This project involved the construction of 2.3 km of gravity sewer at depths up to 4.5 metres and associated manholes and maintenance shafts throughout the township of Smythesdale Victoria.
This was not with out its challenges as we took over the contract from another contractor in which most of the completed works had to be be redone, not to mention it was completed through out the raining winter months at Ballarat due to the tight schedule needed for completion.
This project was completed in 2012.
Referee:
Don Morrison
[email protected]
2012
Construction Date
2.3km
Gravity Sewer
4.5m
Depth